HomeMy WebLinkAbout~Master - Accepting Completion of the Unit 7 Turbine Generator Overhaul Project RESOLUTION NO. 20-212
RESOLUTION ACCEPTING COMPLETION OF
THE UNIT 7 TURBINE GENERATOR OVERHAUL PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Unit 7 Turbine Generator Overhaul Project for the City of Ames,Iowa,in accordance with a contract
dated June 11, 2019, by and between the City of Ames, Iowa, and HPI LLC, of Houston, Texas.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Unit 7 Turbine Generator Overhaul Project has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $764,975.87.
Section 3. The amount due HPI LLC, of Houston, Texas, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 28th day of April, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Martin
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 28t'day of April, 2020.