HomeMy WebLinkAbout~Master - Change Order No. 9 on Contract with HPI, Inc., for Unit 7 Turbine Generator Major Overhaul RESOLUTION NO. 20-093
RESOLUTION APPROVING CHANGE ORDER NO. 9
ON CONTRACT WITH
HPI, INC.,
FOR UNIT 7 TURBINE GENERATOR MAJOR OVERHAUL
FOR THE CITY OF AMES,IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper on the
above Contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that Change Order No. 9 in the amount of$2,675,on contract with HPI,Inc.,of Ames,Iowa,for the
Unit 7 Turbine Generator Major Overhaul be approved and adopted as attached hereto and made a
part hereof by this reference.
ADOPTED THIS 25th day of February, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Beatty-Hansen
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 25'day of February, 2020.
CITY OF CHANGE ORDER NO. 9
Ames"
CONTRACT / BID NO: 2019-120
PURCHASE ORDER NO: 56851
February 11, 2020
Project: I Unit 7 Turbine Generator Overhaul Project
Contractor Name: HPI, LLC Change Orders Approved to Date:
Address: 15534 W Hardy Rd, Suite 220 1 $15,482.45 5 $3,412.50
City, State,&Zip Code: Houston, TX 77060 2 $225,361.55 6 $18,600.75
3 $28,386.00 7 $26,709.00
4 $14,290.00 8 $23,204.94
The contract is modified as follows upon execution of this Change Order. The changes included in this
change order are made in order to cant' out the original intent of the contract. The changes included in
this change order are to be accomplished in accordance with the terms, stipulations, and conditions of
the original contract as though included herein.
DESCRIPTION COST
This change order is for the additional labor for screen replacement delay. $2,675.00
Contract Price:
Original contract rice: $411,464.00
Change orders approved to date: $355,447.19
Amount of this change order: $2,675.00
1 Adjusted contract price including this change order: $769,586.19
Rec men ed by: Accepted by Contractor: ted for Ity of Amps:
6onald E. Kom S" ure John . Haila
Director of Electric Services `` �(�,r Mayor
City of Ames, Iowa Printed Name & Title U City of Ames, Iowa
2— (1� 02 L!Z f�F/,;V 2,,V
Date Date Date