HomeMy WebLinkAboutA012 - Council Action Form dated February 11, 2020, financial security to be released in full, Letter of Credit No. 0450 1o ,
Ame s
Smart Choice
Public Works Department
515 Clark Avenue, Ames, Iowa 50010
Phone 515-239-5160 ♦ Fax 515-239-5404
Item No. 15
February 11, 2020
Honorable Mayor and Council Members
City of Ames
Ames, Iowa 50010
RE: Iowa State University Research Park 3rd Addition Phase IV Financial Security Reduction -
Final
Mayor and Council Members:
The public sanitary sewer extension required as a condition for approval of the final plat of
Iowa State University Research Park 3" Addition Phase IV has been completed in an
acceptable manner by Ames Trenching of Ames, Iowa. The above-mentioned improvement
has been inspected by the Engineering Division of the Public Works Department of the City of
Ames, Iowa, and found to meet City specifications and standards.
As a result of this certification, it is recommended that the financial security for this public
improvement on file with the City for this subdivision be released in full.
Sincerely,
John C. Joiner, P.E.
Director
JJ/nw
cc: Finance, Planning& Housing, Subdivision file
Public Works Department 515.239.5160 main 515 Clark Ave.P.O.Box 811
Engineering 515.239.5404 fax Ames.IA 50010
w.vw.Cityo€Ames.org
SrFIRST
NATIONAL
BANK
AMES • ANKENY • JOHNSTON
VALLEY JUNCTION • WEST DES MOINES
Issue Date: February 12,2019
Irrevocable Letter of Credit No. 0450 RE: ISURP 41h Addition , Ames, Iowa
RE: Iowa State University Research Park
1805 Collaboration Dr. Suite 1250
Ames, Iowa 50010
Ladies/Gentlemen,
We hereby establish our Irrevocable Letter of Credit No.0450 in favor of:
City of Ames
515 Clark
Ames,IA 50010
For the Account of:
Iowa State University Research Park
(0'Addition)
1805 Collaboration Dr. Suite 1250
Ames, Iowa 50010
In the amount of $137,062.00 U.S. Dollars. Irrevocable Letter of Credit No. 0450 will expire on
February 10,2020.
Drafts for payment must be accompanied by the following:
1. Statement indicating which item(s) were not completed under the original estimate of cost
P
submitted to establish this letter of credit.
2. If the item(s) have been partially completed, a statement from the Municipal Engineer as to
the percentage completed of the Specific Item(s)
3. Beneficiary's signed statement indicating that Beneficiary is requesting the cost to complete
the specified incomplete items based on the Municipal Engineer's statement as to percentage
of each item remaining incomplete.
4. Copy of this Irrevocable Letter of Credit No. 0450.
Partial Payments are permitted.
We hereby agree that drafts drawn under and in compliance with the terms of this Letter of Credit will
be duly honored.
This Letter of Credit is subject to the Uniform Customs and Practice of Documentary Credit (1993)
Revision, International Chamber of Commerce Publication#400.
Sincerely,
First National Bank of Ames
By:
e A. Thilg�S®rice President
AMES OFFICE ANKENY OFFICE JOHNSTON OFFICE VALLEY JUNCTION OFFICE WEST DES MOINES OFFICE
405 5th Street 1205 N.Ankeny Blvd. 8460 Birchwood Court,Suite 1100 301 5th Street 5625 Mills Civic Parkway;Suite 100
Ames,IA 50010 Ankeny,IA 50023 Johnston,IA 50131 West Des Moines,IA 50265 West Des Moines,IA 50266
515-232-5561 515-965-3969 515-440-7180 515-274-3483 515-225-2641
Fax 515-232-5778 Fax 515-965-0125 Fax 515-331-2996 Fax 515-274-0173 Fax 515-225-8718
I
2t In
w w w . F N B 2 4 7 . c O m Member FDIC LE NOEq
ISU Research Park Phase IV Sanitary Sewer Extension (Deere Spray Lab)
Item Quantity Unit Unit Price Total
12" Sewer Pipe 1,671 LF $66.00 $110,286.00
Sewer Manhole 6 EA $4,000.00 $24,000.00
Connection to Existing Manhole 1 EA $2,276.00 $2,276.00
COSESCO (Erosion Control) 1 I AC 1 $500.00 $500.00
$137,062.00
FW: Fw: Letter of Credit for 4th Addition
Joel A. Thilges to: dvoss@city.ames.ia.us 02/08/2019 02:45 PM
Diane,
h
Here is the email thread as it relates to the ISURP 4 Addition Letter of Credit.
Joel A.Thilges, Senior Vice President, Commercial Lending
First National Bank
th
405 5 Street, Ames, la 50010
Office—515.663.3025
Cell —515.291.0729
Joel.ThilRes@FNB247.com
NMLS ID# 609252
ISM'
NA
`I MCI.
' N
From: Easter, Nathan A [ISRP] <neaster@iastate.edu>
Sent: Wednesday,January 30, 2019 3:02 PM
To:Joel A.Thilges<Joel.Thilges@FNB247.com>
Cc: Hall, Violetta R [ISRP] <vihall@iastate.edu>; Smith, Alicia L [ISRP] <alismith@iastate.edu>
Subject: FW: Fw: Letter of Credit for 4th Addition
WARNING: This email originated outside of Ames National Corporation.
DO NOT CLICK links or attachments unless you know the content is safe.
Joel,
We'd like to work with you on a letter of credit for$137,062 (as shown in the attached pdf) if you'd be
interested. They won't release our$1.2M LOC (in place with Bankers Trust) until we have this one in
place. We aren't asking around for this one—would just like to go through you if you're interested.
Stay warm!
Thanks,
Nate
From: Nathan Willey<NWillev@city.ames.ia.us>
Sent: Friday,January 25, 2019 1:43 PM
To: Easter, Nathan A [ISRP] <neaster@iastate.edu>
Cc:John C Joiner<JJoiner@city.ames.ia.us>; Diane R Voss<DVoss@city.ames.ia.us>
Subject: RE: Fw: Letter of Credit for 4th Addition
Nate,
Since the quote was a lump sum, I assigned values to each item so we could better
track the LOC (see attached). The 8" services are not included since they are private,
but since I didn't have a value for them, they were not subtracted from the original total.
Let me know if you are ok with that or if you have any questions.
Thank you,
Nathan Willey, P.E.
Civil Engineer 11
nwillev@city.ames.im us
Office:515.239.5436 1 Fax: 515.239.5404
City Hall, 515 Clark Avenue I Ames, IA 50010
CITY OF
s',
www.CityofAmes.ore I ^ Caring People-Quality Programs "Exceptional Service
-----"Easter, Nathan A [ISRP]" <neaster(a)iastate.edu> wrote: -----
To: "Nathan Willey" <NWilleyCabcity.ames.ia.us>
From: "Easter, Nathan A [ISRP]" <neaster(cbiastate.edu>
Date: 01/25/2019 09:22AM
Cc: "John C Joiner" <JJoiner(a)city.ames.ia.us>, "Diane R Voss" <DVoss(a)cit ..ames.ia.us>
Subject: RE: Fw: Letter of Credit for 4th Addition
Nate,
Sounds good, thanks! Attached is Ames Trenching's quote—it is$136,562 because Bill's original $125k
quote was based off an older set of plans that didn't have one run of sanitary/connection/manhole on
it.
So, if my math is correct, here is what I have:
Ames Trenching: $136,562
COSESCO: $500
Total: $137,062
Thanks all,
Nate
From: Nathan Willey<NWilley@city.ames.ia.us>
Sent:Thursday,January 24, 2019 3:49 PM
To: Easter, Nathan A [ISRP] <neaster@iastate.edu>
Cc:John C Joiner<JJoiner@city.ames.ia.us>; Diane R Voss<DVoss@city.ames.ia.us>
Subject: RE: Fw: Letter of Credit for 4th Addition
Hi Nate,
I was planning to reduce the current LOC to about$125,000 for the sanitary sewer, but for some reason,
there was no sanitary included in the original LOC(see attached estimate). Therefore, we will release the
current$1,233,630.67 LOC in full at the next Council meeting and need another LOC for the sanitary
sewer. Can you please send me a copy of the quote from Ames Trenching? An extra $500 would also
need to be added for erosion control (COSESCO). The new LOC total amount would then be Ames
Trenching's quote + $500. Let me know if you have any questions.
Thank you,
Nathan Willey, P.E.
Civil Engineer 11
nwilley@city.ames.ia.us
Office:515.239.5436 1 Fax: 515.239.5404
City Hall,515 Clark Avenue I Ames, IA 50010
CITY F
e s
www.CitvofAmes.org ^ Caring People-Quality Programs^ Exceptional Service "
-----"Easter, Nathan A [ISRP]" <neaster(a)iastate.edu> wrote: -----
To: "John C Joiner" <JJoiner(@city.ames.ia.us>
From: "Easter, Nathan A [ISRP]" <neaster iastate.edu>
Date: 01/24/2019 09:23AM
Cc: "Nathan Willey" <NWilley(cbcity.ames.ia.us>
Subject: RE: Fw: Letter of Credit for 4th Addition
Thanks John, sounds great!
Nate
From:John C Joiner<JJoiner@city.ames.ia.us>
Sent:Thursday,January 24, 2019 9:05 AM
To: Easter, Nathan A [ISRP] <neaster@iastate.edu>
Cc: Nathan Willey<NWilley@city.ames.ia.us>
Subject: Re: Fw: Letter of Credit for 4th Addition
Hi Nate!
We're trying to work this out. I think Steve and Kelly support a reduction and we'll likely
have it on the agenda for Feb 12
CITY 2F-
John C. Joiner, P.E.
Director of Public Works
515.239.5165 desk 1515.239.5404 fax
Hoiner@city.ames.ia.us I City Hall, 515 Clark Avenue Ames, IA 50010
www.CityofAmes.ore I -Caring People-Quality Programs-Exceptional Service"
-----Duane R Pitcher/COA wrote: -----
To: John C Joiner/COA@COA
From: Duane R Pitcher/COA
Date: 01/18/2019 04:08PM
Subject: Fw: Letter of Credit for 4th Addition
John,
I think this is related to your infrastructure improvements.
Duane
Duane Pitcher, CPA, CPFO
Director of Finance
City of Ames
515 Clark Avenue
P.O. Box 811
Ames, Iowa 50010
Phone (515) 239-5114
-----Forwarded by Duane R Pitcher/COA on 01/18/2019 04:07PM -----
To: "Steve Schainker" <SSchainker(&city.ames.ia.us>
From: "Easter, Nathan A [ISRP]" <neaster(&iastate.edu>
Date: 01/17/2019 10:47AM
Cc: "Duane R Pitcher" <DPitcher(&city.ames.ia.us>
Subject: Letter of Credit for 4th Addition
Steve,
Do we still need to have the letter of credit for the 4th Addition Improvements since we have
the EDA and RISE grants approved? We'd like to get that off our books so that we're not
continuing to incur costs there.
Thanks Steve,
Nate
Nathan Easter
Iowa State University Research Park
1805 Collaboration Place, Suite 1250
Ames Iowa 50010
Phone: 515-296-0735
Fax: 515-296-9924
e-mail: neaster(o)iastate.edu
[attachment "image001.gif" removed by Nathan Willey/COA]
[attachment "image002.png" removed by Nathan Willey/COA]
[attachment "image003.gif" removed by Nathan Willey/COA]
[attachment "Nate Easter ISU Industrial Park 3rd Addition Revised.docx" removed by
KEN
o.
Nathan Willey/COA]ISU RP Phase IV Sewer Extension LOC estimate.pdf