HomeMy WebLinkAboutA012 - Resolution No. 14-448 adopted August 12, 2014 RESOLUTION NO. 14448
RESOLUTION ACCEPTING PARTIAL COMPLETION OF
PUBLIC IMPROVEMENTS REQUIRED FOR
SOUTH FORK SUBDIVISION, 6TH ADDITION
FOR THE CITY OF AMES,IOWA
BE IT RESOLVED,by the City Council of the City of Ames, Iowa:
Section One. In accordance with the Certificate of the Public Works Department, the
utilities,base asphalt paving, and curb and gutter construction required as a condition for approval
of the Final Plat of the above-named Subdivision have been completed in an acceptable manner.
Section Two. The bond given to secure performance of the public improvements is hereby
lessened to$23,169.50 for the remaining work that includes asphalt surfacing,street lighting,erosion
control, and final utility fixture adjustments.
ADOPTED THIS 121h day of August, 2014.
C--��? LX,4& AS-W al. coasovAAal
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Goodman
Seconded by: Betcher
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 126'day of August, 2014.
�• A m e s
Smart Choice
Public Works Department
515 Clark Avenue, Ames, Iowa 50010
Phone 515-239-5160 ♦ Fax 515-239-5404
August 7, 2014
Honorable Mayor and Council Members
City of Ames
Ames, Iowa 50010
Ladies and Gentlemen:
I hereby certify that the utilities, base asphalt paving, and curb and gutter construction
required as a condition for approval of the final plat of South Fork, 61h Addition have been
completed in an acceptable manner by Ames Trenching & Excavating of Ames, IA and
Manatts, Inc. of Ames, IA. The above-mentioned improvements have been inspected by the
Engineering Division of the Public Works Department of the City of Ames, Iowa and found to
meet City specifications and standards.
As a result of this certification, it is recommended that the financial security for public
improvements on file with the City for this subdivision be set at $23,169.50. The remaining
work covered by this financial security includes the asphalt surfacing, street lighting,
installation of a shared use path, and final utility fixture adjustments.
Sincerely,
John C.Joiner, P.E.
Director
JJ/jc
cc: Finance, Contractor, Construction Supervisor, PW Senior Clerk, Planning & Housing,
Subdivision file
Public Works Department 515.239.5160 ;,, 515 Clark Ave.P.O.Box 811
Engineering 515.239.5404 f. Ames,IA 50010
South Fork, 61h Addition (REVISED)
August 7, 2014
Page 2
Description Unit Quantity
Class 13 Excavation CY 250
Sub-grade Preparation SY 1,725
4"Sanitary Sewer Service, PVC EA 8
Storm Sewer, RCP 15",CL 3 LF 75
Storm Sewer, RCP 18", CL 3 LF 112
Footing Drain Collector, 6" LF 204
Footing Drain Cleanout,6" EA 2
Footing Drain Outlet and Connection, 6" EA 2
Storm Sewer Service Stub, PVC, 1-1/2" LF 290
Water main,Trenched, PVC,8" LF 290
Water Service Connection,Curb Stop & Box, 1" EA 8
8"45 Degree Bend EA 2
Fire Hydrant Assembly(includes gate valve, boot, 6" pipe and EA 1
fittings)
Intake, SW502 EA 4
Manhole Adjustment, Major EA 1
30" PCC Curb and Gutter LF 790
Pavement,8" HMA SY 485
Pavement, 9.5" HMA SY 1,060
Pavement Removal SY 10
Seeding,Type 1 Lawn Mix ACRE 1
Silt Fence-Install, Maint. & Removal LF 300
Inlet Protection Device-Install, Maint. & Removal EA 3
Stabilized Construction Entrance EA 1