HomeMy WebLinkAboutA013 - Email correspondence regarding S. 16th Street widening :- s Eric Cowles/COA To Diane R Voss/COA@COA
10/01/2009 04:24 PM cc
bcc
Subject Fw:Status of City's Acceptance,of S.1.6th Street:widening ,e
Diane,
I will get a final acceptance letter to you for this tomorrow or Monday.
Thanks.
Eric D. Cowles, P.E.
City of Ames Public Works
Construction Supervisor
515 Clark Avenue
Ames, Iowa 50010
Ph: 515-239-5277
Fax: 515-239-5404
Cell: 515-203-0791
-----Forwarded by Eric Cowles/COA on 10/01/2009 04:23 PM-----
Scott Renaud
r @foxen com>
<slr g. To Eric Cowles<ecowles@city.ames.ia.us>
10/01/2009 04:17 PM cc Corey Mellies<cmellies@city.ames.ia.us>,Tracy Warner
<twarner@city.ames.ia.us>, Edward P Kray
<ekray@city.ames.ia.us>
Subject Re:Status of City's Acceptance of S. 16th Street widening?
Eric - the hydrant will be relocated as per the site plan for the Laverne Apartments. We
need to understand what is required to resolve the issue, if anything. Laverne Apartments
are starting construction yet this year. Thanks. Scott.
Scott Renaud P.E.
Project Manager
FOX Engineering Associates
1601 Golden Aspen Drive
Suite 103
Ames, Iowa 50010
Ph: 515-233-0000
Fax: 515-233-0103
Cell: 515-290-2248
srenaud@foxeng.com
----- Original Message -----
From: "Eric Cowles" <ecowles@city.ames.ia.us>
To: "Scott Renaud" <slr@foxeng.com>
Cc: "Corey Mellies" <cmellies@city.ames.ia.us>, "Tracy Warner"
<twarner@city.ames.ia.us>, "Edward P Kray" <ekray@city.ames.ia.us>
Sent: Thursday, October 1, 2009 4:02:47 PM
Subject: Re: Status of City's Acceptance of S. 16th Street widening?
In talking with Ed the only outstanding issue would be the hydrant on very west end near the Ames
Christian School is leaking. The main from street valve to the hydrant valve has passed pressure testing,
but has not been chlorinated. All of the rest of the water main has passed pressure and bacteria testing.
Eco-Tech is aware of the issue, but we have been told that the hydrant is/was going to be relocated, but
are unsure of exact location and timing. We can look at releasing part or all of the letter of credit, pending
what is going to happen with the hydrant. Let me know how you wish to proceed.
Eric D. Cowles, P.E.
City of Ames Public Works
Construction Supervisor
515 Clark Avenue
Ames, Iowa 50010
Ph: 515-239-5277
Fax: 515-239-5404
Cell: 515-203-0791
Scott Renaud
<slr@foxeng.com> To Eric Cowles<ecowles@city.ames.ia.us>,Corey Mellies<cmellies@city.ames.ia.us>,Tracy
09/30/2009 02:35 PM Warner<twarner@city.ames.ia.us>
cc
Subje Status of City's Acceptance of S. 16th Street widening?
ct
Eric - when can we expect the City to accept the S.16th Street widening project and release
the letters of credit. We are holding retainage for Eco-Tech pending the final acceptance. I
assume all the concrete breaks were good and there are no punch list issues. Please give
me an update. Thanks. Scott.
Scott Renaud P.E.
Project Manager
FOX Engineering Associates
1601 Golden Aspen Drive
Suite 103
Ames, Iowa 50010
Ph: 515-233-0000
Fax: 515-233-0103
Cell: 515-290-2248
srenaud@foxeng.com