HomeMy WebLinkAbout~Master - Completion of Furnishing 15kV Outdoor Metalclad Switchgear and 69kV Control Panels for Top-O-Hollow Substation Expansion and Breaker Addition Project RESOLUTION NO. 20-031
RESOLUTION ACCEPTING COMPLETION OF
FURNISHING 15KV OUTDOOR METALCLAD SWITCHGEAR AND 69KV CONTROL
PANELS FOR TOP-0-HOLLOW SUBSTATION EXPANSION AND BREAKER
ADDITION PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Furnishing l5kV Outdoor MetalClad Switchgear and 69kV Control Panels for Top-0-Hollow
Substation Expansion and Breaker Addition Project for the City of Ames,Iowa,in accordance with
a contract dated November 28,2017,by and between the City of Ames,Iowa,and Harold K. Scholz
Company, of Ralston,Nebraska.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Furnishing 15kV Outdoor MetalClad Switchgear
and 69kV Control Panels for Top-O-Hollow Substation Expansion and Breaker Addition
Project has been fully completed by the Contractor in accordance with the terms of the
contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $599,231.40 (inclusive of Iowa sales tax).
Section 3. The amount due Harold K. Scholz Company,of Ralston,Nebraska,is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 14`'' day of January, 2020.
Diane R. Voss, City Clerk John A. Haila, Mayor
Introduced by: Corrieri
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Junck, Martin,
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 14t'day of January, 2020.