HomeMy WebLinkAbout~Master - Change Order No. 2 for North River Valley Low-Head Dam RESOLUTION NO. 19-577
RESOLUTION APPROVING CHANGE ORDER NO. 2
ON CONTRACT WITH
RW EXCAVATING SOLUTIONS
FOR NORTH RIVER VALLEY LOW-HEAD DAM
FOR THE CITY OF AMES, IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper on the
above Contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that Change Order No. 2 in the amount of$40,662.90, on contract with RW Excavating Solutions
of Prairie City, Iowa, for the North River Valley Low-Head Dam be approved and adopted as
attached hereto and made a part hereof by this reference.
ADOPTED THIS 12`h day of November, 2019.
Diane . Voss, City Clerk John A. Haila, Mayor
Introduced by: Nelson
Seconded by: Corded
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 121h day of November, 2019.
CITY OF CHANGE ORDER NO. 2
Ames CONTRACT/ BID NO: 2018-108
PURCHASE ORDER NO: 55420
October 29,2019
Project:I North River Valley Park Low Head Dam Improvements
Contractor Name: RW Excavating Solutions, LC Change Orders Approved to Date:
Address: 13293 S 88'"Ave W 1 $3,900.0 33
City,State,&Zip Code: Prairie City,IA 50228 2 1 14
The contract is modified as follows upon execution of this Change Order. The changes included in this change order are made
in order to carry out the original intent of the contract. The changes included in this change order are to be accomplished in
accordance with the terms,stipulations,and conditions of the original contract as though included herein.
ACTION DESCRIPTION I COST
720 cu.yds. Crusher Run material at$48.00/cu.yd.for construction of channel and
bank features to the extents and elevations shown on the plans. Quantity of material
Add included with original contract was not sufficient for completion of work. $34,560.00
178 cu.yds. Class E material at$76.05/cu.yd. for construction of channel and bank
features to the extents and elevations shown on the plans. Quantity of material
Add included with original contract was not sufficient for completion of work. $13,536.90
Line Item#10—Install Backfill; Material that was thought to be in channel for reuse
Remove was not available. ($7,434.00)
Contract Price:
Original contract price: $776,534.88
Change orders approved to date: $3,900.00
Amount of this change order: $40,662.90
Adjusted contract price including this change order: $821,097.78
Accepted for RW Excavating Solution LC: City of Ames Approval:
(Water& Pollution Control Department)
Signature Date tin ure Date
Printed Name&Title: Ames Approval (Mayor Haila):
Signature Date