RESOLUTION APPROVING CHANGE ORDER NO. 1
ON CONTRACT WITH
EARTH SERVICES & ABATEMENT (ESA)
FOR ASBESTOS REMEDIATION AND RELATED SERVICES AND SUPPLY
CONTRACT FOR THE POWER PLANT
FOR THE CITY OF AMES,IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper on the
above Contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that Change Order No. 1 in the amount of$74,000, on contract with Earth Services &Abatement
(ESA) of Des Moines, Iowa, for the Asbestos Remediation and Related Services and Supply
Contract for the Power Plant be approved and adopted as attached hereto and made a part hereof by
this reference.
ADOPTED THIS 22°d day of October, 2019.
cr
Diane AVoss. City Clerk John A. Haila, Mayor
Introduced by: Betcher
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 22"d day of October, 2019.
CITY OF CHANGE ORDER NO. 1
s
CONTRACT / BID NO: 2019-141
A m e PURCHASE ORDER NO: 056987
October 17, 2019
Project: I Asbestos Maintenance Services Contract
Contractor Name: Earth Services &Abatement, LLC Change Orders Approved to Date:
Address: 1901 Easton Blvd 1 4
City,State,&Zip Code: Des Moines, IA 50316 2 5
3 6
The contract is modified as follows upon execution of this Change Order. The changes included in this
change order are made in order to carry out the original intent of the contract. The changes included in
this change order are to be accomplished in accordance with the terms, stipulations, and conditions of
the original contract as though included herein.
DESCRIPTION COST
Earth Services & Abatement to perform additional asbestos removal on Unit 7
and Unit 8 piping during the remainder of the fiscal year. The projects include
removing asbestos from additional piping on Unit 7 before it is put back online this
year and removing material on Unit 8 main steam line around the turbine, while it is
in reserve shutdown. This work will be invoiced according to time and materials $74,000.00
used at the rates agreed upon in the Asbestos Remediation and Related
Services and Supply Contract for Power Plant 2019-141.
Contract Price:
Original contract rice: $80,000.00
Change orders approved to date: $0.00
Amount of this change order: $74,000.00
Adjusted contract price including this change order: $154,000.00
; end77---
d: cepted b Contractor: c pted for City of Ames:
16 1 A LJk?.�&
Do Id Kom, Director Stature ohn A. Haila, Mayor
City of Ames Electric Services ( City of Ames, Iowa
Printed Name &Title
zz ���� /, 10 /2i1►y t .2Z.
Date IDate Date