HomeMy WebLinkAbout~Master - Completion of Water Pollution Facility Screw Pump Drive Replacement Project RESOLUTION NO. 19-536
RESOLUTION ACCEPTING COMPLETION OF
WATER POLLUTION CONTROL FACILITY SCREW
PUMP DRIVE REPLACEMENT PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS,the Water Pollution Control Facility has filed a certificate of completion for the
Water Pollution Control Facility Screw Pump Drive Replacement Project for the City of Ames,
Iowa, in accordance with a contract dated December 11, 2018, by and between the City of Ames,
Iowa, and Weidner Construction, Inc., Marshalltown, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Water Pollution Control Facility Screw Pump Drive
Replacement Project has been fully completed by the Contractor in accordance with the
terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $114,897.
Section 3. The amount due Weidner Construction,Inc.,of Marshalltown,Iowa,is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8t'day of October, 2019.
Diane . Voss, City Clerk John A. Haila, Mayor
Introduced by: Beatty-Hansen
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 8th day of October, 2019.