HomeMy WebLinkAbout~Master - Completion of Distributed Control System (DCS) RESOLUTION NO. 19-117
RESOLUTION ACCEPTING COMPLETION OF
DISTRIBUTED CONTROL SYSTEM (DCS)
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Distributed Control System(DCS)Project for the City of Ames,Iowa,in accordance with a contract
dated March 23,2015,by and between the City of Ames,Iowa,and Emerson Process Management
Power&Water Solutions, Inc. of Pittsburgh, Pennsylvania.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Distributed Control System(DCS)Project has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $1,973,055.31.
Section 3. The amount due Emerson Process Management Power&Water Solutions,
Inc. of Pittsburgh, Pennsylvania, is hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 26th day of March, 2019.
Diane R. Voss, City Clerk John . Haila, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin
Voting nay: None Absent: Nelson
Resolution declared adopted and signed by the Mayor this 26th day of March, 2019.