HomeMy WebLinkAboutA013 - Letter dated August 13, 2002 certifying completion of base paving Public W® k
e
CaringPeoppk 515 Clark Avenue, Ames, Iowa 50010
Qualify Programs Phone 515-239-5160 A Fax 515-239-5404
FxceNlmpuil Service
August 13, 2002
Honorable Mayor and Council Members
City of Ames s I '
Ames, Iowa 50010
Ladies and Gentlemen:
I hereby certify that the base paving required as a condition for approval of the final
plat of Dauntless Subdivision, 7th Addition has been completed in an acceptable
manner by Manatt's Inc. The above mentioned improvement has been inspected by
the Engineering Division of the Public Works Department of the City of Ames, Iowa
and found to meet city specifications and standards.
As a result of this certification it is recommended that the financial security for public
improvements on file with the City for this subdivision be reduced to $14,250.00 for
the remaining work that includes the surface paving and street lighting.
Sidewalks and bike path also remain to be completed, but will be covered under a
separate agreement that does not require financial security.
I further certify that the quantities of the completed work are as follows:
Descry° f�on � 7 � ��� �
Dickinson Avenue Pavement Extension
31' wide 6" asphalt base, w/30" PCC curb & gutter l.f. 562
Sincerely,
Paul D. Wiegand, E.
Public Works Director
PDW/dwj
cc: City Cleric, Finance, Contractor, PW Administrative Assistant, Construction
Supervisor, and Planning & Housing Director