HomeMy WebLinkAbout~Master - Completion of New Water Treatment Plant - Contract 2 RESOLUTION NO. 19-076
RESOLUTION ACCEPTING COMPLETION OF
NEW WATER TREATMENT PLANT - CONTRACT 2
FOR THE CITY OF AMES, IOWA
WHEREAS, the Water Treatment Plant has filed a Certificate of Completion for the New
Water Treatment Plant-Contract 2 for the City of Ames,Iowa,in accordance with a contract dated
October 14,2017,by and between the City of Ames,Iowa,and Knutson Construction Services,Inc.,
of Minneapolis, Minnesota.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the New Water Treatment Plant- Contract 2 has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $53,163,561.
Section 3. The amount due Knutson Construction Services, Inc. of Minneapolis,
Minnesota is hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 26th day of February, 2019.
`1
Diane R. Voss, City Clerk John . Haila, Mayor
Introduced by: Betcher
Seconded by: Beatty-Hansen
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 26th day of February, 2019.