RESOLUTION ACCEPTING COMPLETION OF
POWER PLANT MAINTENANCE SERVICES CONTRACT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Power Plant Maintenance Services Contract for the City of Ames, Iowa, in accordance with a
contract dated June 11,2013,by and between the City of Ames,Iowa,and ProEnergy Services LLC
of Sedalia, Missouri.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Power Plant Maintenance Services Contract has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $4,250.
Section 3. The amount due ProEnergy Services LLC of Sedalia, Missouri, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 23rd day of October, 2018.
�11d�
Diane R. Voss, City Clerk John . Haila, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 23`d day of October, 2018.