HomeMy WebLinkAbout~Master - Accepting Completion of 2016 CyRide Interceptor Pit Upgrades Project RESOLUTION NO. 18-423
RESOLUTION ACCEPTING COMPLETION OF
2016 CYRIDE INTERCEPTOR PIT UPGRADES PROJECT
FOR THE CITY OF AMES
WHEREAS,the Transit Board of Trustees has filed a certificate of completion for the 2016
CyRide Interceptor Pit Upgrades Project for the City of Ames, Iowa, in accordance with a contract
dated August 23, 2016,by and between the City of Ames, Iowa, and Woodruff Construction, LLC
of Ames, Iowa.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
as follows:
Section 1. The total contract for the 2016 CyRide Interceptor Pit Upgrades Project
has been fully completed by the Contractor in accordance with the terms of the
contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $266,492, with an unpaid balance of
$13,325.
Section 3. The amount due Woodruff Construction, LLC of Ames, Iowa, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 10`'' day of July, 2018.
`1
Diane R. Voss, City Clerk John . Haila, Mayor
Introduced by: Gartin
Seconded by: Betcher
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 10'day of July, 2018.