RESOLUTION ACCEPTING COMPLETION OF
CONSTRUCTION OF THE AMES PLANT TO N.E. ANKENY 161KV TRANSMISSION
LINE RELOCATION FOR THE CITY OF AMES, IOWA
WHEREAS, the Contractor has filed a certificate of completion for the Construction of the
Ames Plant to N.E. Ankeny 161kV Transmission Line Relocation for the City of Ames, Iowa, in
accordance with a contract dated October 11, 2016, by and between the City of Ames, Iowa, and
Hooper Corporation of Madison, Wisconsin.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Ames Plant to N.E. Ankeny 161 kV Transmission
Line Relocation has been fully completed by the Contractor in accordance with the terms
of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $950,032.43.
Section 3. The amount due Hooper Corporation of$130,223.31 is hereby ordered paid
as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 22"d day of May, 2018.
`1
Diane R. Voss, City Clerk John . Haila, Mayor
Introduced by: Betcher
Seconded by: Gartin
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 22°d day of May, 2018.