HomeMy WebLinkAbout~Master - Completion of Turbine Control System, Bid No. 1 RESOLUTION NO. 18-143
RESOLUTION ACCEPTING COMPLETION OF
TURBINE CONTROL SYSTEM, BID NO. 1 FOR
POWER PLANT FUEL CONVERSION PROJECT
FOR THE CITY OF AMES, IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Turbine Control System, Bid No. 1 for the Power Plant Fuel Conversion Project for the City of
Ames, Iowa, in accordance with a contract dated April 14, 2015, by and between the City of Ames,
Iowa, and G.E. Energy Control Solutions, Inc., of Longmont, Colorado.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Turbine Control System, Bid No. 1 for the Power
Plant Fuel Conversion Project has been fully completed by the Contractor in accordance
with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $1,159,706.60.
Section 3. The amount due G.E. Energy Control Solutions, Inc., of Longmont, Colorado,
is hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 27" day of March, 2018.
IT-r - I--- ? I 1JL4; -A
Diane R Voss, City Clerk John . Haila, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 27t' day of March, 2018.