RESOLUTION ACCEPTING COMPLETION OF
2016/17 ASPHALT STREET PAVEMENT IMPROVEMENTS (NORTHWOOD DRIVE,
THOMPSON DRIVE, TRAIL RIDGE ROAD, TRAIL RIDGE CIRCLE,AND IDAHO
AVENUE)AND 2016/17 WATER SYSTEM IMPROVEMENTS PROGRAM #2 -
WATER MAIN REPLACEMENT
FOR THE CITY OF AMES, IOWA
WHEREAS, the Public Works Department has filed a certificate of completion for the
2016/17 Asphalt Street Pavement Improvements (Northwood Drive, Thompson Drive, Trail Ridge
Road, Trail Ridge Circle, and Idaho Avenue) and 2016/17 Water System Improvements Program#2
- Water Main Replacement for the City of Ames, Iowa, in accordance with a contract dated March 7,
2017,by and between the City of Ames, Iowa, and Manatt's, Inc., of Brooklyn, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the 2016/17 Asphalt Street Pavement Improvements
(Northwood Drive, Thompson Drive, Trail Ridge Road, Trail Ridge Circle, and Idaho
Avenue) and 2016/17 Water System Improvements Program #2 - Water Main
Replacement has been fully completed by the Contractor in accordance with the terms
of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $1,771,615.94.
Section 3. The amount due Manatt's, Inc., of Brooklyn, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 27th day of March, 2018.
Diane R. Voss, City Clerk John . Haila, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin, Martin,Nelson
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 27th day of March, 2018.