November 30,2015
Honorable Mayor and Council Members
City of Ames
Ames, Iowa 50010
Ladies and Gentlemen:
I hereby certify that the public utility improvement, 12-inch water main installation, required
as a condition for approval of the final plat of Dauntless,5th Addition has been completed in an
acceptable manner. The above-mentioned improvement has been inspected by the
Engineering Division of the Public Works Department of the City of Ames, Iowa and found to
meet City specifications and standards.
During review of the City's records it was discovered that the financial security for the
referenced subdivision was not released following installation of the public improvements in
2001. As a result of this certification, it is recommended that the financial security for public
improvements on file with the City for this subdivision ($27,400)-b Ge_a e1 aged infull'.
Sincerely,
John C.Joiner, P.E.
Director
JJ/jc
cc: Finance, Contractor, Construction Supervisor, PW Senior Clerk, Planning& Housing,
Subdivision file
77-7
Public Works Department 5:15 239 51;so xhu, 515,CIark Ave::P.O Box 81-1
Engmeenng, 515 239!5404.fdc' Amesjl lA 50010
www GityofAmes,arg �
Dauntless,5th Addition
November 30, 2015
Page 2
Description Unit Quantity
12"WATER MAIN LF 682
HYDRANT ASSEMBLY(NEW) EA 1
HYDRANT ASSEMBLY(REMOVE AND RELOCATE) EA 1
12"WATER VALVE EA 1
WALL PIPE REACTION BLOCK EA 1
CONSTRUCTION SURVEY LS 1