HomeMy WebLinkAbout~Master - Completion of 2016/17 Specialized Wet Dry Vacuum, Hydro Blast, and Related Cleaning Services for Power Plant RESOLUTION NO. 17-538
RESOLUTION ACCEPTING COMPLETION OF
SPECIALIZED WET DRY VACUUM, HYDRO BLAST,AND RELATED CLEANING
SERVICES FOR POWER PLANT
FOR THE CITY OF AMES, IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Specialized Wet Dry Vacuum, Hydro Blast, and Related Cleaning Services for the Power Plant for
the City of Ames, Iowa, in accordance with a contract dated May 13, 2014, by and between the City
of Ames, Iowa, and Bodine Services of Clinton, LLC, of Clinton, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Specialized Wet Dry Vacuum, Hydro Blast, and
Related Cleaning Services for the Power Plant has been fully completed by the
Contractor in accordance with the terms of the contract and is hereby accepted and
approved.
Section 2. The total cost of the contract is $73,298.97.
Section 3. The amount due Bodine Services of Clinton, LLC, of Clinton, Iowa, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 22"d day of August, 2017.
/ , ;Rr-,,A- - -) -Yka& 4004-0 UV.
Diane R. Voss, City Clerk Arm H. Campbell, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 22" day of August, 2017.