HomeMy WebLinkAbout~Master - CyRide Bus Turnaround construction at Storm Street and Welch Avenue RESOLUTION NO. 17490
RESOLUTION APPROVING CITY CONTRIBUTION TO
CONSTRUCTION OF CYRIDE BUS TURNAROUND
FOR THE CITY OF AMES
WHEREAS, the Ames Transit Agency's Transit Board of Trustees approved the concept of
a turnaround for CyRide's new Gold Route as part of the System Redesign Plan; and,
WHEREAS, the turnaround will be located south of Storm Street at Welch Avenue on Iowa
State University property, this turnaround will be the end point of this route, allowing the bus to turn
around and operate back to campus and areas north; and,
WHEREAS, the turnaround concept was developed as a result of discussions with the South
Campus Area Neighborhood (SCAN) around and near the Wallace/Wilson Residence Halls served
by this new Gold Route; and,
WHEREAS, the original proposal was to operate this new route to the two residence halls
and then utilize Hayward Avenue between Stone and Knapp to turn the bus around and return to
Campus and north to Schilletter Village; and,
WHEREAS, residents indicated that this service change would impact the amount of traffic
and noise on their street and neighborhood, with buses operating on the route every 10 minutes
Monday through Friday; and,
WHEREAS, as a result, they requested that Transit Board members and CyRide staff develop
an alternative that would not increase transit impacts to their neighborhood; the bus turnaround on
ISU property was the resolution to this challenge and allows for the route to operate efficiently and
effectively while reducing current and proposed transit impacts on the SCAN neighborhood; and,
WHEREAS, CyRide staff has worked with ISU Facilities Planning and Management staff
to develop a final construction cost estimate for the turnaround, and this cost is estimated to be
$185,000, which includes design, construction and minimal landscaping costs; and,
WHEREAS, ISU Facilities and Planning will be responsible for construction of the bus
turnaround, and is ready to proceed with bids and construction once funding is approved; and,
WHEREAS, at its June 28, 2017, Transit Board meeting, Board members approved CyRide's
finding commitment and tentatively agreed to a cost-sharing approach to fund this project (subject
to final approval by each of the fiinding partners); and,
WHEREAS, the proposal requires CyRide to find 50% of the construction cost from its
operating closing balance, and each of the three funding partners (City of Ames, Iowa State
University, and ISU Student Government) to contribute the remaining 50%, divided into three equal
shares of$30,833 each as a one-time capital cost; and,
WHEREAS, it should be noted that the requested City contribution is in addition to the City's
annual contribution to CyRide from the City's Transit levy.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the one-time capital outlay of $30,833 for this Bus Turnaround project is hereby approved,
contingent upon approval by Iowa State University and ISU's Student Government to both provide
$30,833 towards construction of the Bus Turnaround at Storm Street and Welch Avenue.
ADOPTED THIS 8" day of August, 2017.
Diane R Voss, City Cleric Ann H. Campbell, Mayor
Introduced by: Nelson
Seconded by: Betcher
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 8" day of August, 2017.