WHEREAS, the Airport Improvements Program in the City's 2015/16 Capital Improvements
Plan includes a project to construct a new terminal building, itinerant hangar, and related site
improvements at the Ames Municipal Airport; and,
WHEREAS, Bolton & Menk was originally hired to design the Terminal Site Work and
Building Design, which has been completed with fees totaling$437,864; and,
WHEREAS, now, as part of the construction phase of the project, the design team of Bolton
& Menk and Alliance Architects (subcontractors to B&M) will be hired under a Construction
Services contract to perform critical tasks such as 1) shop drawing review, 2) provide on-site
clarifications to the builder, and 3) coordinate change orders with the overall design; staff has
conducted an evaluation of the proposed scope and cost of$80,000, and found it to be reasonable
and appropriate for this project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Addendum to the Engineering Services Agreement with Bolton & Menk to add construction
services in an amount not to exceed$80,000 is hereby approved.
ADOPTED THIS 13th day of June, 2017.
C-A�"'K � A.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 13th day of June, 2017.