HomeMy WebLinkAbout~Master - Contract and bond for Non-Asbestos Insulation and Related Services and Supplies for Power Plant RESOLUTION NO. 17-273
RESOLUTION APPROVING CONTRACT AND BOND FOR
NON-ASBESTOS INSULATION AND RELATED SERVICES AND SUPPLIES
AT POWER PLANT
FOR THE CITY OF AMES, IOWA
Section 1. The contract between the City of Ames, Iowa, and Total Insulation Mechanical,
Inc., of Ames, Iowa, dated the 26th day of April, 2016, for the Non-Asbestos Insulation and
Related Services and Supplies for the Power Plant as provided for in the detailed plans and
specifications referred to in the preamble hereof, and the performance bond of the said
contractor with Western Surety Company of Sioux Falls, South Dakota, as surety thereon, in
the amount of$80,000.00 filed in connection therewith, be and the same are hereby approved.
Section 2. All resolutions or order or parts thereof in conflict herewith are hereby repealed to
the extend of such conflict.
ADOPTED THIS 9th day of May, 2017.
(:�A_ - - —A. V. Cam,,
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson
Voting nay: None Absent: Orazem
Resolution declared adopted and signed by the Mayor this 9th day of May, 2017.