HomeMy WebLinkAboutA008 - Letter to Mayor and Council dated December 15, 1992, certifying completion of sanitary sewer, water main and street paving r l
/�
CITY OF AMES , I owA 50010
Public Works Department
515 Clark
515-239-5160
A „ December 15, 1992
F! , ,-.;?
Honorable Mayor and Council Members 4 DEC 1 6 !
City of Ames
Ames, Iowa 50010 --
..............
CITY CLERK
CITY OF AMES,IOWA
Ladies and Gentlemen:
I hereby certify that the sanitary sewer, water main, and street paving in Valley
East Subdivision, Plat 3 has been completed in an acceptable manner by Rhiner's
Plumbing Co. , Construct Inc. , and Manatt's Inc. and has been inspected by the
Engineering Division of the Public Works Department of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
ITEM DESCRIPTION UNIT PRICE QUANTITY AMOUNT
---------------------------------------------------------------------------------
SEE ATTACHMENT
PROJECT TOTAL $65,474.32
Sincerely,
Paul D. Wiegand,P.E.
Public Works Director
Approve by:
T. Robert Kindred, Assistant City Manager
PDW/kg
cc: City Clerk, Finance, Contractor, PW Adm. Asst. , PW Const. Supr.
AMES — THE CENTER OF IT ALL
s
ITEM DESCRIPTION UNIT PRICE QUANTITY AMOUNT
----------------------------------------------------------------------------------
PLAT 3
SANITARY SEWER
1 Connection to existing Ea. 300.00 1.0 300.00
2 8" sewer pipe l.f. 20.25 480.0 9,720.00
3 Manhole Ea. 1315 2.0 2,630.00
TOTAL SANITARY: 12,650.00
WATER MAIN
1 Connection to existing Ea. 300.00 2.0 600.00
2 8" water pipe l.f. 13.00 405.0 5,265.00
3 Install hydrant run Ea. 280.00 1.0 280.00
4 8" x 6" tee Ea. 245.00 1.0 245.00
TOTAL WATER: 6,390.00
STORM SEWER
1 Subgrade preparation s.y. 1.10 3384.0 3,722.40
2 Concrete curb and gutter l.f. 8.45 1846.0 15,598.70
3 Asphalt base, 6.5" s.y. 10.17 2666.0 27,113.22
TOTAL STREET: 46,434.32
GRAND TOTAL: $65,474.32