HomeMy WebLinkAboutA019 - Letter to Mayor and Council dated January 13, 1994, certifying completion of sanitary sewer, water main, storm sewer and street construction C�o
"ES C I T Y O F A M E S
II
P.O.BOX 811 AMES IOWA 50010
Community-University-Opportunity
Public Works Dept. .. -
515-239-5160
January 13, 1994
AN G
CITY CLF;RK 4
CITY OF AMES,IOY-A
Honorable Mayor and Council Members
City of Ames
Ames, Iowa 50010
Ladies and Gentlemen:
I hereby certify that the sanitary sewer, water main, storm sewer and street
construction in Valley East Subdivision have been completed in an acceptable manner by
Rhiner Plumbing, Con-Struct, and Manatt's and have been inspected by the Engineering
Division of the Public Works Department of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
SEE ATTACHMENT
Sincerely,
Paul D.Wiegand,P.E.
Public Works Director
Approved b
,'d Z'-j'j
T. R ert Kindred, Assistant City Manager
PDW/kg
c: City Clerk, Finance, Contractor, PW Admin.Asst. , Construction Supervisor
l�
Item Description Unit Price Quantity Total
Plat I
1 Asphalt Surface S.Y. 2.35 5,128.0 12,050.80
Plat 2
2 Asphalt Surface S.Y. 2.35 2,666.0 6,265.10
Plat 3
3 Asphalt Surface S.Y. 2.26 1,541.0 3,482.66
Plat 4
Sanitary Sewer
4 8" Sanitary sewer l.f. 21.00 442.0 9,282.00
5 Sanitary sewer manhole ea. 1,315.00 2.0 2,630.00
Water Main
6 8" Water main l.f. 15.00 506.0 7,590.00
7 6" Water main l.f. 14.00 120.0 1,680.00
8 Fire hydrants ea. 280.00 2.0 560.00
9 8" x 6" tee ea. 245.00 2.0 490.00
10 8" x 6" reducer ea. 145.00 1.0 145.00
11 8" 45° bend ea. 145.00 1.0 145.00
12 8" 22-j° bend ea. 145.00 1.0 145.00
Storm Sewer
13 12" RCP l.f. 17.00 136.0 2,312.00
14 Open throat intake ea. 1,500.00 1.0 1,500.00
Street Paving
15 Subgrade preparation S.Y. 1.10 3,424.0 3,766.40
16 30" PCC curb and gutter l.f. 8.75 1,035.0 9,056.25
17 Asphalt base S.Y. 10.17 3,021.0 30,723.57
$91,823.78