HomeMy WebLinkAbout~Master - Completion of Water Plant High Service Pump #3 Replacement Project RESOLUTION NO. 16-536
RESOLUTION ACCEPTING COMPLETION OF
WATER TREATMENT PLANT HIGH SERVICE PUMP#3
REPLACEMENT PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Water and Pollution Control Department has filed a certificate of
completion for the Water Treatment Plant High Service Pump#3 Replacement Project for the City
of Ames, Iowa, in accordance with a contract dated October 27, 2015, by and between the City of
Ames, Iowa, and Northway Well and Pump Company of Waukee, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Water Treatment Plant High Service Pump #3
Replacement Project has been fully completed by the Contractor in accordance with the
terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $69,500.00.
Section 3. The amount due Northway Well and Pump Company of Waukee, Iowa, is
hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 13`h day of September, 2016.
ci��"--R A.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Betcher
Seconded by: Gartin
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 13"'day of September, 2016.