RESOLUTION APPROVING FUNDING AGREEMENT FOR
2016/17 CYRIDE ROUTE PAVEMENT IMPROVEMENTS
(SOUTH 3RD STREET AND SOUTH 4TH STREET)
FOR THE CITY OF AMES
WHEREAS,this is the annual program for pavement improvements to streets that are or were
bus routes, and many of these streets were designed and built for lighter traffic; and,
WHEREAS,with these streets now designated as bus routes,accelerated deterioration of the
street surface has occurred,and pavement improvements will provide a street section that will carry
higher traffic volumes, thus reducing maintenance needs and providing better rideability for the
public; and,
WHEREAS,the location for 2016/17 is South 3rd Street(South Grand Avenue to South Duff
Avenue) and South 4th Street(Squaw Creek to South Grand Avenue); and,
WHEREAS,this project is shown in the 2016-2021 Capital Improvements Plan with funding
in the amount of$525,000 from General Obligation bonds, $555,000 from Road Use Tax, $50,000
from Electric Utility Fund, and $1,292,000 from MPO/STP funds; and,
WHEREAS, it is anticipated that the project will have a February 2017 letting, which will
be through the Iowa Department of Transportation(Iowa DOT), with construction in 2017.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Iowa Department of Transportation Agreement for MPO/STP Funding for the 2016/17
CyRide Route Pavement Improvements (South 3" Street and South 4`' Street) is hereby approved.
ADOPTED THIS 23rd day of August, 2016.
A.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Betcher
Seconded by: Nelson
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None