HomeMy WebLinkAbout~Master - Completion of Year 3 Contract for Lime Sludge Disposal Operation RESOLUTION NO. 16-441
RESOLUTION ACCEPTING COMPLETION OF
YEAR 3 FOR LIME SLUDGE DISPOSAL OPERATION
FOR THE CITY OF AMES,IOWA
WHEREAS, the Water and Pollution Control Department has filed a certificate of
completion for the Lime Sludge Disposal Project(Year 3)for the City of Ames,Iowa,in accordance
with a contract dated May 28, 2013, by and between the City of Ames, Iowa, and Wulfekuhle
Injection&Pumping, Inc., of New Vienna, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Lime Sludge Disposal Project (Year 3) has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $334,030.12.
Section 3. The amount due Wulfekuhle Injection & Pumping, Inc., of New Vienna,
Iowa, is hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 26`h day of July, 2016.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Betcher
Seconded by: Nelson
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 26`h day of July, 2016.