HomeMy WebLinkAboutA014 - Letter dated August 13, 1979 certifying completion of street construction C
a E ... T.d
CITY _RK
i Q ,{M L �ovy 4
AUG. 11 !4 1979.
August 13, 1979
Honorable Mayor and Council Members
City of Ames, IA 50010
Ladies and Gentlemen:
I hereby certify that the street construction on Garden Road, Ely Circle, Viola
Mae Avenue, Duluth Street, Minnetonka Avenue and Teagarden Drive in Southdale
Third Addition to Ames, Iowa has- been completed in an acceptable manner in accord-
ance with the plans and specifications. of the City of Ames, :Iowa, and has been
inspected by the Engineering Department of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
1977 Prices:
Unit
Item Description Quantity Unit Price Amount
1 . Concrete curb and gutter 923.5 l .f. $ 4.95 $ 4,571 .33
2. Sub-base preparation 1 ,544 S.Y. 0.40 617.60.
3. Asphalt base 417 tons 18.75 7,818.75
4. Prime and tack 98 gal . 0.70 68.60
5. Adjust manhole 2 ea. 115.00 230.00
6. Adjust water valve 1 ea. 95.00 95.00
TOTAL 1977 PRICES $ 13,401 .28
1979 Prices:
Unit
Item Description Quan-tity Unit Price Amount
1 . Concrete curb and gutter 5,256 l .f. $ 5.30 $ 27,856.80
2. Sub-base preparation 10,131 S.Y. 0.40 4,052.40
3. Asphalt base 2,541 tons 20.06 50,972.46
4. Asphalt surface 960 tons 30.22 29,011 .20
5. Prime and tack 1 ,071 . gal . 0.75 803.25
6. Adjust manhole 10 ea. 115.00 11150.00
7. Adjust intake 15 ea. 75.00 1 ,125.00
TOTAL 1979 PRICES $114,971 .11
- 2
Additional 1979 Work:
Unit
Item Description Quantity_ Unit Price Amount
1 . Hot-mix base 23.93 tons $ 25.00 $ 598.25
2. Asphalt surface 15 tons 35.00 525.00
3. Curb and gutter 58 l .f. 8.00 464.00
4. Sub-base preparation 106 S.Y. 0.60 63.60
5. Tree removal 1 ea. 150.00 150.00
TOTAL ADDITIONAL WORK $ 1 ,800.85
GRAND TOTAL $130,173.24
Sincerely,
A. 0. Chantland, P. E.
Public Works Director
4APPROVEDel , City Manager
AOC: sh
cc: Conservative Mortgage Company
Iowa Road Builders
Finance Department