RESOLUTION APPROVING PROFESSIONAL SERVICES AGREEMENT FOR
CONSTRUCTION OF NORTH RIVER VALLEY WELL FIELD PROJECT
FOR THE CITY OF AMES
WHEREAS, on February 20, 2015, a request for proposals (RFP) for engineering services
was issued for the route determination and design of the pipeline associated with the City's new well
field; and,
WHEREAS, after a thorough review of each firm's proposal, staff determined that HDR
Engineering was the most qualified firm for both the route determination and design of the project;
and,
WHEREAS, when negotiating the scope of work with HDR, staff learned that the level of
uncertainty in the route resulted in some additional costs being included in HDR's proposal for the
final design phase; as a result, staff decided to limit the initial scope of services to just the route
determination portion,with the intent to negotiate the design services after the study phase had been
completed; and,
WHEREAS, on May 12, 2015,the City Council approved the initial scope of services with
HDR for only the route study services in the amount of$37,500; the route study has since been
completed, and a pipeline alignment was chosen based on the recommendation by HDR and
feedback from various stakeholders; and,
WHEREAS, it should be noted that it may be necessary to acquire private property for
construction of the actual wells, and,
WHEREAS, City staff worked closely with the Electric Services Department and the Parks
and Recreation Department during the process of the route study; and,
WHEREAS, staff also invited all potentially affected property owners to an open house on
March 1,2016;the open house allowed the public to ask questions and give feedback regarding the
alternative pipeline route alignments and planned well locations; and,
WHEREAS, on April 26, 2016, City Council approved a resolution to fund the final site
specific design and to acquire, by condemnation if necessary, property and easements for the
construction of the North River Well Field and Pipeline Project; and,
WHEREAS,following the approval by Council, staff worked with HDR to develop a scope
of services for the actual design of the project, and this project will be a joint design effort by City
staff and HDR; and,
WHEREAS, City staff will design the new wells,while HDR will design the pipeline;HDR
will also design the power supply for the site,to include both Ames Electric for primary service and
the installation of a standby generator for emergency power; and,the Electric Services Department
has worked closely with W&PC staff to ensure that the scope of work for the electrical design
includes all necessary requirements; and,
WHEREAS, after finalizing the scope of services with HDR, its final proposed fee for
completing the design, bid, and construction phase engineering services is $384,200.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the contract for engineering services with HDR Engineering, Inc., of Des Moines, Iowa, for
design,bidding, and construction phase engineering services for the North River Valley Well Field
Project in an amount not to exceed$384,200 is hereby approved.
ADOPTED THIS 28th day of June, 2016.
0AA�V10R, tom• GOPiis.�i
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Nelson
Seconded by: Corrieri
Voting aye: Beatty-Hansen, Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 28th day of June, 2016.