HomeMy WebLinkAbout~Master - Grant Agreement amendment for Squaw Creek Water Main Protection Project RESOLUTION NO. 16-124
RESOLUTION APPROVING GRANT AGREEMENT FOR SQUAW CREEK WATER
MAIN PROTECTION PROJECT (HAZARD MITIGATION GRANT PROGRAM
FLOOD MITIGATION)
FOR THE CITY OF AMES
WHEREAS, following flooding in 2010, Public Works staff submitted 11 projects for
consideration under the Federal Emergency Management Agency's(FEMA)Hazard Mitigation Grant
Program(HMGP), and nine of the projects were denied federal funding due to failure to achieve a
benefit cost analysis greater than 1.0; and,
WHEREAS, on June 26, 2012, City Council directed staff to continue pursuing federal
funding for the Stuart Smith Park Bank Stabilization project, and this has been named the Squaw
Creek Water Main Protection project by Iowa Homeland Security and Emergency Management
Department(HSEMD); and,
WHEREAS, Municipal Engineer Tracy Warner was designated as the City's authorized
representative for the project, and a local match was approved up to $120,000; and,
WHEREAS, included in the 2012-2017 Capital Improvements Plan (CIP) was a program
entitled Flood Response and Mitigation Projects that included$820,000 in General Obligation Bonds
and $325,000 in Storm Sewer Utility Funds, and portions of this funding were used on a flood
mitigation project in Northridge Subdivision/Moore Memorial Park and for bank stabilization near
Utah Drive and another location near North Riverside; and,
WHEREAS, these three projects are now complete, and the two remaining projects are the
Trail Ridge Landslide and the Squaw Creek Water Main Protection project; and,
WHEREAS, unspent local funding totaling $628,737 has been carried forward through
budget amendments; and,
WHEREAS, an engineering consultant was hired to complete the HMGP Drainage Project
Application,which was submitted in July 2012,and the proposed construction proj ect included sheet
pile walls and riprap infill for bank stabilization to protect the existing 24-inch water main under
Squaw Creek on the south side of Lincoln Way; and,
WHEREAS, in September 2012, the City was notified that this project was considered
stacked, which meant that the funding cap was reached by other projects for the specific disaster
covering this project; and,
WHEREAS,in 2015,staff was notified that FEMA was interested in breaking up the project
into phases, which included Phase I that would fund further analysis of the problem and the best
proposed solution,including consideration of whether the existing low-head dam should be removed
or remain in place as part of the project; the City Council approved the Phase I agreement on
May 26, 2015, where FEMA funded 75%, the State funded 10%, and the City funded 15% of the
cost; and,
WHEREAS, the original September 2012 analysis called for sheet piling as the primary
means of bank stabilization along with a rock riffle/rapids to mitigate the effects of the dam,and the
alternative recommended in the October 2015 report to progress toward Phase II (construction) is
based on a stream restoration approach utilizing integrated/bioengineering techniques; and,
WHEREAS,bank stabilization techniques would consist of flattening the banks,construction
of benches within the banks,utilization of revetment stone for stabilization at lower elevations (up
to the bench),and structural soil(soil filled rock)with native plantings at elevations above the bench,
and the project would also consist of installing a rock flume (rip rap) downstream of the low head
dam to eliminate the eddy pool contributing to the bank erosion; and,
WHEREAS, considering the current and future risk to the existing infrastructure,restoring
a gradual transition downstream of the dam is recommended;this option is considered the most cost-
effective to achieve the objectives and would also improve ecological functions and aquatic habitat,
as well as reduce the area disturbed by the project; and,
WHEREAS, staff received notification on March 2, 2015, that the FEMA grant has been
approved for Phase II, which would include final design, permitting, and construction of the
alternative described above; and,
WHEREAS,if this agreement is approved,a request for professional services proposals will
be requested for Phase II(final design,permitting,and construction),and once proposals are received
and rated by City staff for work associated with FEMA and HSEMD's recommended Phase II work
tasks, a contract will be brought back to City Council
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Grant Agreement with FEMA/Iowa Homeland Security for Phase II of the Squaw Creek
Water Main Protection Project is hereby approved, authorizing the City to contribute 15% and
FEMA and the State of Iowa to pay 85% of the Phase II contract.
ADOPTED THIS 22nd day of March, 2016.
A. tom• ���
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Nelson
Seconded by: Betcher
Voting aye: Betcher, Beatty-Hansen, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 22nd day of March, 2016.