HomeMy WebLinkAbout~Master - Change Orders for 2015/16 Airport Terminal Building & Hangar (Site Work) RESOLUTION NO. 16-080
RESOLUTION APPROVING CHANGE ORDER NO. 4
ON CONTRACT WITH
ABSOLUTE CONCRETE CONSTRUCTION OF SLATER, IOWA,
FOR 2015/16 AIRPORT TERMINAL BUILDING AND HANGAR-
(PHASE 1: SITE WORK)
FOR THE CITY OF AMES,IOWA
WHEREAS, it has been determined that a Change Order is necessary and proper on the
above contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that Change Order No. 4 on contract with Absolute Concrete Construction of Slater, Iowa, for the
2015/16 Airport Terminal Building and Hangar(Phase 1: Site Work)be approved and adopted as
attached hereto and made a part hereof by this reference.
ADOPTED THIS 23rd day of February, 2016.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Gartin
Seconded by: Corrieri
Voting aye: Betcher, Beatty-Hansen, Corrieri, Gartin,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 23rd day of February, 2016.