WHEREAS, as an annual requirement of the Federal Aviation Administration (FAA), the
City submits an Airport Improvements Program (AIP) to the FAA showing the next five Federal
Fiscal Years of airport projects; and,
WHEREAS, the information contained in the Federal AIP is then copied into the Airport
Improvements Program of the City's own Capital Improvement Plan(CIP)to ensure the obligation
of local matching funds required for each project; and,
WHEREAS, the proposed AIP five-year program project list is as follows:
The proposed AIP 5-year program project list is as follows:
FFY=Federal Fiscal Year
Project Description FFY 2017 FFY 2018 FFY 2019 FFY 2020 FFY 2021
Masterplan Update $166,000
Electrical Vault& Terminal Demolition $396,000
Runway 01/19 Justification Report $ 14,000
Environmental Assessment, RW 01/19 $100,000
Annual Totals $166,000 $ - $410,000 $100,000 $ -
Funding Source:
Federal/State Funds $149,400 $356,400 $ 90,000
Local Funds $ 16,600 $ 53,600 $ 10,000
WHEREAS, the remaining projects are in the Long Range Needs Assessment (LRNA),
which are those remaining steps necessary to extend the main Runway 01/19 to a length of
approximately 8,000 feet, and this will include land acquisition (2022), grading (2023), road
realignment(2024), and paving (2025).
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the 2017-2021 Federal Airport Improvements Program is hereby approved.
ADOPTED THIS 8t'day of December, 2015.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Corrieri
Seconded by: Nelson
Voting aye: Betcher, Corrieri, Gartin,Nelson, Orazem
Voting nay: Goodman Absent: None
Resolution declared adopted and signed by the Mayor this 8t'day of December, 2015.