HomeMy WebLinkAbout~Master - Completion of Methane Engine - Generator Set No. 2 Rehabilitation Project at WPC Facility RESOLUTION NO. 15-731
RESOLUTION ACCEPTING COMPLETION OF
METHANE ENGINE-GENERATOR SET NO. 2 REHABILITATION PROJECT
AT WATER POLLUTION CONTROL FACILITY
FOR THE CITY OF AMES,IOWA
WHEREAS, Barr Engineering Company, consulting engineer, has filed a certificate of
completion for the Methane Engine-Generator Set No. 2 Rehabilitation Project at the Water
Pollution Control facility for the City of Ames,Iowa,in accordance with a contract dated August 27,
2013,by and between the City of Ames, Iowa, and Ziegler Power Systems of Altoona, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Methane Engine-Generator Set No.2 Rehabilitation
Proj ect at the Water Pollution Control facility has been fully completed by the Contractor
in accordance with the terms of the contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $176,608.00.
Section 3. The amount due Ziegler Power Systems of Altoona,Iowa,is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 8th day of December, 2015.
t"'R
1) A.
C�AAA'V Iiii-e
. 6t�aw
Diane . Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Nelson
Seconded by: Goodman
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 8t' day of December, 2015.