March 6, 1992.
Honorable Mayor and Council Members G - ------
City of Ames
Ames, Iowa 50010
APR2 21992
Ladies and Gentlemen: Ci i Y Ui- Rit�
Cirl Of AMES, 10'04A
I hereby certify that the Utility construction in the Patio Homes West
Subdivision, has been completed in an acceptable manner by Rhiner Plumbing of Des
Moines and has been inspected by the Engineering Division of the Public Works
Department of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
ITEM DESCRIPTION .UNIT PRICE QUANTITY AMOUNT
---------------------------------------------------------------------------------
SEE ATTACHMENT
Sincerely,
Paul D. Wiegand,I.E.
Public Works Director
Approve by:
-(10�-.
T. Robert Kindred, Assistant City Manager
PDW/kg
cc: City Clerk, Finance, Contractor, P.W. Admin. Asst. , P.W.Constr. Suprv.
AMES— THE CENTER OF IT ALL
a
Page 2
ITEM DESCRIPTION UNIT PRICE QUANTITY AMOUNT
----------------------------------------------------------------------------------
STORM SEWER
1 24" R.C.P. L.F. 124
2 21" R.C.P. L.F. 64
3 18" R.C.P. L.F. 424
4 15" R.C.P. L.F. 405
5 12" R.C.P. L.F. 99
6 MANHOLES EA. 1
7 INTAKES EA. 5
SANITARY SEWER
8 8" SEWER PIPE L.F. 74
WATER MAIN
9 6" WATER PIPE L.F. 550
10 6" TEE EA. 1
11 6" 45 DEGREE BEND EA. 1
12 6" VALVE EA. 2
13 SET HYDRANT EA. 1
PROJECT TOTAL $40,641.00