HomeMy WebLinkAbout~Master - Completion of Power Plant Unit #7 Feedwater Heater Replacement RESOLUTION NO. 15-625
RESOLUTION ACCEPTING COMPLETION OF
POWER PLANT UNIT #7 FEEDWATER HEATER REPLACEMENT PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Water and Pollution Control Department has filed a certificate of
completion for the Power Plant Unit#7 Feedwater Heater Replacement Project for the City of Ames,
Iowa, in accordance with a contract dated December 9, 2014, by and between the City of Ames,
Iowa, and American Exchanger Services, Inc., of Hartford, Wisconsin.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Unit#7 Feedwater Heater Replacement Project has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $300,055.00.
Section 3. The amount due American Exchanger Services,Inc.,of Hartford,Wisconsin,
is hereby ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 131h day of October, 2015.
_ Aea4w
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Betcher
Seconded by: Corrieri
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 131h day of October, 2015.