HomeMy WebLinkAboutA019 - Letter dated December 9, 1981 certifying completion of storm sewer construction December 9, 1981
Honorable Mayor and Council Members
City of Ames
Ames , Iowa 50010
Ladies and Gentlemen :
I hereby certify that the storm sewer construction within Patio Homes West
First Addition to Ames, Iowa, and on Ontario Road has been completed in
an acceptable manner by H & F Builders, Inc. , of Ames, Iowa in accordance
with the plans and specifications of the City of Ames, Iowa, and inspected
by the Engineering Division of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
Unit
Item Description Quantity Unit Price Amount
1. 12" R.C.P. 173 l . f. $ 8.50 $ 1,470.50
2. 12" R.C.P. 130 l .f. 10.50 1 ,365.00
3. 18" R.C.P. 120 l .f. 12.25 1,470.00
4. 24" R.C.P. 73 l . f. 20.00 1,460.00
5. 24" F.E.S. 1 each 172.00 172.00
6. 30" R.C.P. 228 l .f. 22.00 5,016.00
7. 36" R.C.P. 542 l .f. 32.00 17,344.00
8. 48" R.C.P. 10 l . f. 50.00 500.00
9. Type "D" Intake 2 each 640.00 1,280.00
10. Type "E" Intake - 6 each 600.00 3,600.00
11. Beehive Intake 2 each 150..00 300.00
12. RA-18 Intake 1 each 1 ,200.00 1,200.00
13. Standard manhole 2 each 1 ,000.00 2,000.00
14. Standard 48" T-Section conversion 1 each 1,100.00 1,100.00
15. Shot Rock Rip-Rap 3 tons 15.00 45.00
Total $ 38,322.50
; f
Honorable Mayor and Council Members
Page Two
December 9, 1981
The City's share of the costs for the shared storm. sewer and for the non
development of the south and west properties is $3,992.35.
SinceVy,
U' jE�
Arnold 0. Chantland, P.E.
Public Works Director
Approved by:
y
i
ohn W, Elwell , City Manager
Cf J
cc: H F udders
Finance Department
Public Works Department
City Manager's Office
City Clerk