HomeMy WebLinkAboutA011 - Letter dated January 10, 1983 certifying completion of street construction January 10, 1983
Honorable Mayor and Council Members
City of Ames
Ames, Iowa 50010
Ladies and Gentlemen:
I hereby certify that the street construction on Eisenhower Drive from Buchanan
Drive to Bloomington load in 18th Addition to Parkview Heights Subdivision of
Ames, Iowa has been completed in an acceptable manner by Manatts, Inc. , of Ames,
Iowa, in accordance with the plans and specifications of the City of Ames, Iowa,
and has been inspected by the Engineering Division of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
Work performed at 1980 prices:
Unit
Item Description Quantity Unit Price Amount
1. Concrete curb and gutter 1910 l.f. $ 6.40 $ 12,224.00
2. Subbase preparation 3527 S.Y. 0.50 1,763.50
3. Asphalt base 932.2 tons 25.50 23,771.10
4. Prime and tack 270 gal. 1.25 337.50
5. Manhole adjustment 4 ea. 125.00 500.00
6.. Intake adjustment 7 ea. 90.00 630.00
Total $ 39,226. 10
Work performed at 1982 prices:
1. Asphalt surface 327 tons $ 36.00 $ 11,772.00
2. Prime and tack 290 gal. 1.30 377.00
Total $12,149.00
Grand Total $ 51,375. 10
Z
gan ,*E.
Public Works Director
Approved By:
Steven L. Schainker, City Manager
AOC/dj
CC: H & F Builders
Manatts, Inc.
Finance Dept.
Public Works Dept.
��=
Ci y -C e rk