HomeMy WebLinkAbout~Master - Completion of Year 2 of Water Biosolids Hauling and Digester Cleaning Project RESOLUTION NO. 15-432
RESOLUTION ACCEPTING COMPLETION OF
WATER POLLUTION CONTROL FACILITY THREE-YEAR BIOSOLIDS HAULING
AND DIGESTER CLEANING PROJECT
FOR THE CITY OF AMES, IOWA
WHEREAS, the Water and Pollution Control Department has filed a certificate of
completion of Year Two of the Water Pollution Control Facility Three-Year Biosolids Hauling and
Digester Cleaning Project for the City of Ames, Iowa, in accordance with a contract dated July 8,
2014,by and between the City of Ames, Iowa, and Nutri-Ject, Inc., of Hudson, Iowa.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Year Two of the Water Pollution Control Facility
Three-Year Biosolids Hauling and Digester Cleaning Project has been fully completed
by the Contractor in accordance with the terms of the contract and is hereby accepted and
approved.
Section 2. The total cost of the contract is $95,803.73.
Section 3. The amount due Nutri-Ject, Inc., of Hudson, Iowa, is hereby ordered paid as
provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 14`h day of July, 2015.
Lxa& A.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Nelson
Seconded by: Goodman
Voting aye: Betcher, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: Corrieri