HomeMy WebLinkAbout~Master - Completion of MEC Interconnection 161-kV Line Construction RESOLUTION NO. 15-309
RESOLUTION ACCEPTING COMPLETION OF
MEC INTERCONNECTION 161-KV LINE CONSTRUCTION
FOR THE CITY OF AMES, IOWA
WHEREAS, DGR Engineering has filed a certificate of completion for the MEC
Interconnection 161-kV Line Construction for the City of Ames,Iowa,in accordance with a contract
dated October 23, 2012, by and between the City of Ames, Iowa, and Hooper Corporation of
Madison, Wisconsin.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the MEC Interconnection 161-kV Line Construction has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $9,108,766.74.
Section 3. The amount due Hooper Corporation of Madison, Wisconsin, is hereby
ordered paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 12th day of May, 2015.
C�:51�"R LXIA&
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Betcher
Seconded by: Goodman
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 12tb day of May, 2015.