January 6, 1994
Honorable Mayor and Council Members
City of Ames
Ames, Iowa 50010
Ladies and Gentlemen:
I hereby certify that the sanitary sewer, watermain, storm sewer, and street paving in
Northridge Parkway Subdivision, 4th, 5th, 6th, 7th, 8th, and loth Additions have been
completed in an acceptable manner by Van Hauen & Associates and Manatt's Inc. and has
been inspected by the Engineering Division of the Public Works Department of the City
of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
SEE ATTACHMENT
Project Total $278,978.18
Sincerely,
D. ("I �
Paul D.Wiegand,P.E.
Public Works Director
Approved by. :
T. Robert Kindred, Assistant City Manager
PDW/kg
c: City Clerk, Finance, Contractor, PW Admin.Asst. , Construction Supervisor
r^
Item Description Unit Price Quantity y Total
4TH ADDITION
1 Asphalt surface S.Y. 2.35 1055.0 2,479.25
5TH & 6TH ADDITIONS
2 Asphalt surface S.Y. 2.35 4800.0 11,280.00
7TH & 8TH ADDITIONS
3 Asphalt surface S.Y. 2.26 3095.0 6,994.70
LOTH ADDITION
4 Manholes ea. 1,300.00 7.0 9,100.00
5 8" PVC truss pipe l.f. 33.00 1448.0 47,784.00
6 8" PVC SDR-18 l.f. 20.00 2047.0 40,940.00
7 6" Ductile iron hydrant runs l.f. 20.00 51.0 1,020.00
8 8" bends @ 45° ea. 125.00 3.0 375.00
9 8" bends @ 22Z° ea. 125.00 1.0 125.00
10 8" bends @ 11--` ea. 125.00 1.0 125.00
11 Tee's 8" x 8" x 6" ea. 125.00 4.0 500.00
12 Tee's 8" x 8" x 8" ea. 100.00 2.0 200.00
13 8" Cross ea. 150.00 1.0 150.00
14 8" Valves ea. 300.00 8.0 2,400.00
15 16" Casing l.f. 100.00 66.0 6,600.00
16 12" RCP 1.f. 20.00 462.0 9,240.00
17 18" RCP l.f. 20.00 781.0 15,620.00
18 21" RCP l.f. 30.00 114.0 3,420.00
19 Open throat intakes ea. 900.00 11.0 9,900.00
20 Storm manhole ea. 1,200.00 1.0 1,200.00
21 Subgrade preparation S.Y. 1.10 8390.0 9,229.00
22 30" PCC curb and gutter l.f. 8.35 4524.0 37,775.40
23 Asphalt base ton 27.90 2240.9 62,520.83
--------------
--------------
Project Total $278,978.18
--------------