HomeMy WebLinkAbout~Master - Airport Improvements Architectural and Engineering Agreements RESOLUTION NO. 15-089
RESOLUTION APPROVING ARCHITECTURAL AND ENGINEERING SERVICES
AGREEMENT FOR AIRPORT TERMINAL BUILDING
AND STORAGE HANGAR PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, On February 10, 2015, staff presented a report updating City Council on the
status of the Airport Terminal Building and Storage Hangar project,which included a brief historical
summary of improvements conducted at the Ames Municipal Airport, a project time line showing
critical dates for replacement of the terminal building, a funding summary, a financing and storage
hangar agreement with Iowa State University(ISU),a discussion of consultant design services,and
important next steps necessary to address the ongoing financial stability of the Airport through an
updated Fixed Base Operator(FBO) operating agreement; and,
WHEREAS, the next step is to secure professional architectural and engineering design
services to facilitate preparation of the new terminal/hangar building site improvements so that ISU
and the private sector can construct the hangar portion of the project during the summer of 2015;
and,
WHEREAS,the total project budget is$2,410,000,which includes$867,000 in G.O.Bonds,
$943,000 in revenue abated bonds, $150,000 in a State of Iowa vertical infrastructure grant, and
$450,000 in federal funds; and,
WHEREAS, the design and construction covered in the site improvements phase of the
project is anticipated to utilize all the available federal funds($450,000).,and those funds represent
three years of accrued federal entitlements given annually to all general aviation airports across the
nation; and,
WHEREAS,Bolton&Menk,Inc.,has been selected to perform these professional services,and
his project will be led by Bolton&Menk's aviation group and coordinated out of its Ames office; and,
WHEREAS,through a selection process,Bolton&Menk was found to be the most qualified
consultant based upon a combination of past aviation experience and its proposed approach to this
project; and,
WHEREAS, while the site improvements are being designed, it is proposed that the
consultants conduct a parallel effort to begin the architectural design of the terminal building itself,
and,
WHEREAS, this effort will include continued project coordination with those who are
constructing the storage hangar, as well as conducting at least four stakeholder meetings to further
refine the final configuration and aesthetics of the terminal building; and,
WHEREAS,the end goal will be to have one complete facility to serve as a gateway to the
Ames community while at the same time meeting the future growth needs of the Airport; and,
WHEREAS, staff is recommending that the Council approve two separate design contracts
for professional services—the first is for the site improvements design,which follows the standards
set by the FAA,in an amount not to exceed$140,000,and the second contract is for the architectural
design of the terminal building,which includes stakeholder meetings and design coordination with
the hangar portion, with the contract amount not to exceed $260,000.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Professional Services Agreements for the Airport Terminal Building Project with Bolton&
Menk, Inc., of Ames, Iowa, for design of the site improvements, at a cost not to exceed$140,000,
and for the building design, at a cost not to exceed $260,000, are hereby approved.
ADOPTED THIS 24`h day of February, 2015.
--1YAa& A.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Goodman
Seconded by: Corrieri
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 24"'day of February, 2015.