HomeMy WebLinkAbout~Master - Engineering Services Agreement for 2014/15 Downtown Pavement Improvements Project RESOLUTION NO. 14-577
RESOLUTION APPROVING ENGINEERING SERVICES AGREEMENT FOR 2014/15
DOWNTOWN STREET PAVEMENT IMPROVEMENTS (5TH STREET)
FOR THE CITY OF AMES,IOWA
WHEREAS,this annual program is for the rehabilitation/reconstruction of streets within the
downtown area(Lincoln Way to 7th Street and Grand Avenue to Duff Avenue),and,in the past,these
projects have involved pavement reconstruction, rehabilitation of storm and sanitary sewers, and
street scapes; and,
WHEREAS,the location for FY 2014/15 is 5t1i Street from Burnett Avenue to Grand Avenue;
and,
WHEREAS, this design project will include at least two public informational meetings,
design of pavement improvements, drainage analysis and design of appropriate storm sewer
improvements, as well as evaluation of the existing sanitary and storm sewer pipe structure; and,
WHEREAS, services to be performed by the consultant include base survey, evaluation of
construction techniques,preparation of plans and specifications,notification and coordination with
right-of-way users and adjacent land owners, and attendance at the pre-construction meeting; and,
WHEREAS, on February 25,2014,the City Council authorized applications for two water
quality grants for improvements along 5th Street and around the City Hall complex,and the City has
now successfully received a State Revolving Fund(SRF) Sponsored Project grant; and,
WHEREAS, these water quality improvements may include soil quality restoration,
converting all cool season turf grass along street right-of-way and at City Hall complex to native turf
(e.g.Buffalo Grass),planting of native forbs and grasses,installation ofpermeable pavers in parking
stalls, and installation of bioretention cells; and,
WHEREAS, these improvements, while improving water quality in our community, will
significantly change the appearance of the City Hall complex; and,
WHEREAS, the native turf will not be regularly mown nor fertilized, which is standard
procedure with standard lawn care, and each of these water quality practices installed will help
mitigate the water quality volume and reduce peak stormwater flows; and,
WHEREAS,the project design scope includes water quality design services in coordination
with the 5th Street project; and,
WHEREAS, proposals for this work were received from nine engineering firms and were
evaluated; and,
WHEREAS, staff has negotiated a contract with the highest ranked firm,Bolton&Menk of
Ames, Iowa, and this consultant has a strong history of providing excellent water quality projects
throughout Iowa and Minnesota,as well as integrating water quality features into street projects;and,
WHEREAS, Bolton & Menk has a strong record of successfully designing City projects,
coordinating with property owners, and being innovative in approaching project designs; and,
WHEREAS,although the cost of the second highest ranked firm is significantly lower,these
characteristics of Bolton&Menk give staff confidence that they will provide the best value for the
engineering design services on this particular project.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Engineering Services Agreement for the 2014/15 Downtown Street Pavement Improvements
(51h Street) with Bolton & Menk of Ames, Iowa, in an amount not to exceed $91,520 is hereby
approved.
ADOPTED THIS 10" day of November, 2014.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Nelson
Seconded by: Orazem
Voting aye: Betcher, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: Corrieri
Resolution declared adopted and signed by the Mayor this 1 Oth day of November, 2014.