HomeMy WebLinkAbout~Master - Master Engineering Services Agreement for design of New Water Treatment Plant Project RESOLUTION NO. 14-551
RESOLUTION APPROVING AMENDMENT TO MASTER ENGINEERING SERVICES
AGREEMENT WITH FOX ENGINEERING
FOR DESIGN OF NEW WATER TREATMENT PLAN
FOR THE CITY OF AMES,IOWA
WHEREAS, on September 8, 2009, the City Council awarded a professional services
agreement to FOX Engineering Associates of Ames to initiate the final design, bidding, and
construction of the new Water Treatment Plant; and,
WHEREAS,that agreement was executed in the form of a Master Agreement that included
all of the over-arching terms and conditions,as well as a series of task orders executed over time that
contain details of the specific work elements to be provided; and,
WHEREAS, there is a discrepancy in the termination date of the agreement between the
Master Agreement and one of the task orders; and,
WHEREAS,the Master Agreement,approved by the City Council on October 13,2009,calls
out in Paragraph 3.01(A) that, "This Agreement shall be effective and applicable to Task Orders
issued hereunder for five(5)years from the Effective Date of the Agreement,"and the effective date
of the agreement was the date of Council authorization, giving a termination date of October 13,
2014; and,
WHEREAS, Task Order 4.1, approved by the City Council on August 28,2012, included a
statement that the term of work shall be"...24 months following the issuance of the Notice of Final
Acceptance of the construction work related to this project," and the completion date for Knutson
Construction Services under Contract 2 is July 25, 2017; and,
WHEREAS, based on this clause, the effective termination date of the Master Agreement
would be July 25, 2019; and,
WHEREAS, staff felt it was appropriate to issue an addendum to the Master Agreement,
clarifying the existing language in Paragraph 3.01(A)to read,"This Agreement shall be effective and
applicable to Task Orders issued hereunder for five (5) years from the Effective Date of the
Agreement, except in the event that final construction is not completed within five years, in which
event the term of the Master Agreement shall be extended to 24 months following the issuance of the
Notice of Final Acceptance of the construction work related to this project, as provided for in
paragraph 5(a) of Task Order 4.1"; and,
WHEREAS, with this change,both the Master Agreement and Task Order 4.1 would be in
agreement and would call for the same end date to the Master Agreement.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the amendment to the Master Agreement with FOX Engineering to adjust the term of the
agreement to run until 24 months following issuance of the Notice of Final Acceptance of the
construction work related to the new Water Treatment Plant project is hereby approved.
ADOPTED THIS 28" day of October, 2014.
_ { . add, Ate, qr/ cam,,
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Goodman
Seconded by: Corrieri
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson
Voting nay: None Absent: Orazem
Resolution declared adopted and signed by the Mayor this 28"day of October, 2014.