HomeMy WebLinkAbout~Master - Professional Services Agreement for Grand Avenue Extension Location & Environmental Study RESOLUTION NO. 14-458
RESOLUTION APPROVING PROFESSIONAL SERVICES AGREEMENT FOR
GRAND AVENUE EXTENSION LOCATION AND ENVIRONMENTAL STUDY
FOR THE CITY OF AMES,IOWA
WHEREAS,in preparation for a future proj ect to extend Grand Avenue from South 3rd Street
to South 16' Street and the realignment and extension of South 5th Street between South Duff
Avenue and Grand Avenue,location and environmental studies must be performed for this corridor,
prior to transitioning into the other phases of project development outlined in the Capital
Improvements Plan(CIP); and,
WHEREAS, the study area for this project consists of the extension of Grand Avenue and
two intersection improvement areas, including at South 5th Street and South Duff Avenue and at
South 16" Street and South Duff Avenue; and,
WHEREAS, the project scope focuses on the completion of services and deliverables to
provide project management assistance, development of a location study, and necessary National
Environmental Policy Act (NEPA) documentation; and,
WHEREAS, proposals for this work were received from four engineering firms and were
evaluated; and,
WHEREAS, typically on City projects, the proposed cost is a consideration when scoring
submitted proposals;however,since Federal Demonstration Funds(earmarks)are funding a portion
of this project,Iowa DOT standards state staff can only enter negotiations for funding amounts after
an engineering firm is selected through the approved Iowa DOT consultant selection process; and,
WHEREAS,therefore,staff has negotiated a contract with the highest ranked firm,Howard
R. Green, Inc. from Johnston, Iowa, in the amount of$315,150.23; and,
WHEREAS,the project study area includes a large portion of the floodway and fringe areas,
which has led to a goal to construct the proposed bridge and roadway at an elevation to prevent
overtopping during high water events; and,
WHEREAS, the project scope has become more complex and will be completed over the
course of two phases,and it is anticipated that those two phases will be completed sequentially over
the course of two fiscal years; and,
WHEREAS,the Iowa Department of Transportation has reviewed the professional services
agreement and scope of services for phase one, and has given concurrence to moving forward with
this project and the selected consultant; and,
WHEREAS, this project will be funded by $300,000 in General Obligation Bonds and
approximately $104,000 in Federal Demonstration Funds that are included in the 2013/14 CIP,
bringing total available funding to approximately$404,000
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Ames, Iowa,
that the Engineering Services Agreement with Howard R. Green, Inc., of Johnston, Iowa, in an
amount not to exceed$315,150.23 for the Grand Avenue Extension-Location and Environmental
Study is hereby approved.
ADOPTED THIS 20h day of August, 2014.
Lfka . A. vY/ Cis.
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Orazem
Seconded by: Betcher
Voting aye: Betcher, Corrieri, Gartin, Goodman,Nelson, Orazem
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 261h day of August, 2014.