HomeMy WebLinkAboutA008 - Letter to Mayor and Council dated November 8, 1984, certifying completion of sanitary sewer, storm sewer and water main November 8, 1984
Honorable Mayor and Council Members
City of Ames
Ames, IA. 50010
Ladies and Gentlemen:
I hereby certify that the following sanitary sewer, storm sewer, and water main
construction on Ironwood Court in Gateway II Subdivision has been completed in
an acceptable manner by Gaar Constructors, Inc. of Des Moines and Con- Struct,
Inc. of Ames, in accordance with the specifications and has been inspected by
the Engineering Division of the Public Works Department of the City of Ames,
Iowa.
I further certify that the quantities of the completed work are as follows:
Item Description Quantity Unit Amount
Sanitary Sewer
1. 8" truss pipe 3,151 l.f. $ 62,120.00
2. Manholes 15 ea. 18,000.00
3. Manhole drops 2 ea. 1,500.00
4. Embedment rock 192.7 ton 2,312.40
Sanitary Sewer Total $83,932.40
Water Main
1. 8" D.I.P. 290 l.f. $ 4,350.00
2. 8" P.V.C. 1,366 l.f. 16,500.00
3. 6" P.V.C. 592 l.f. 5,200.00
4. 12" x 8" tap 1 ea. 1,950.00
5. 14" dia. steel casing 100 l.f. 6,500.00
6. Set hydrants, valves, and
accessories 6 ea. $ 6,480.00
Water Main Total $ 40,980.00
Storm Sewer
1. Site grading $ 19,195.00
Mayor and Council Members
November 8, 1984
Page Two
Item Description Quantity Unit Amount
Storm Sewer Cont'd.
2. Storm sewer 19,370.00
12" R.C.P. 344 l.f.
13.5" x 22" arched R.C.P. 212 l.f.
18" R.C.P. 110 l.f.
3. 6" sump collector 570 l.f. 9,700.00
Storm Sewer Total $ 48,265.00
Grand Total $ 173,177.40
Sinc rely,
V / '
A 0. Chan land, P.E.
Public Works Director
Approved by:
Steven L. Schainker, City Manager
AOC/dj
cc: City Manager, City Clerk, Public Works, Finance, Paul Hinderaker, Gaar Con-
structors, Con-Struct, Inc. , Story Construction, and Design Collaborative