August 4, 1987
Honorable Mayor and Council Members
City of.Ames
Ames, IA. 50010
Ladies and Gentlemen:
I hereby certify that the street construction in Country Gables 7th Addi-
tion has been completed in an acceptable manner by Des Moines Asphalt &
Paving of Ames, Iowa , in accordance with the plans and specifications and
has been inspected by the Engineering Division of the Public Works Depart-
ment of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
Item Description Quantity Unit Amount
1. Curb & gutter 2,025 l.f. Lump Sum
2. Asphalt base 933 ton Lump Sum
3. Asphalt surface 435 ton Lump Sum
Total $ 46,705.00
Sincerely,
G
.0. Chantland, P.E
Public Works Director
Approved by:
Steven L. Schainker, City Manager