HomeMy WebLinkAbout~Master - Completion of Vet Med Substation Capacitor Banks RESOLUTION NO. 12-603
RESOLUTION ACCEPTING COMPLETION OF
VET MED SUBSTATION CAPACITOR BANKS
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Vet Med Substation Capacitor Banks Project for the City of Ames, Iowa, in accordance with a
contract dated January 24,2012,by and between the City of Ames,Iowa,and Controllix Corporation
of Walton Hills, Ohio.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Vet Med Substation Capacitor Banks Project has
been fully completed by the Contractor in accordance with the terms of the contract and
is hereby accepted and approved.
Section 2. The total cost of the contract is $218,379.
Section 3. The amount due Controllix Corporation of Walton Hills, Ohio.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 27"' day of November, 2012.
�"'-RIlAad A044-0
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Davis
Seconded by: Orazem
Voting aye: Davis, Goodman, Larson, Orazem, Szopinski, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 27th day of November, 2012. is hereby
ordered paid as provided by law.