January 13, 1994
E _Fz'
i
Al 8
Honorable Mayor and Council Members CITY cLs�Ft"
City of Ames 'qTr 100
Ames, Iowa 50010 -
Ladies and Gentlemen:
I hereby certify that the sanitary sewer., water main, storm sewer and street paving in
Brookview Place-First Addition have been completed in an acceptable manner by Rhiner
Plumbing, Con-Struct Inc. , and Manatt's Inc. and have been inspected by the Engineering
Division of the Public Works Department of the City of Ames, Iowa.
I further certify that the quantities of the completed work are as follows:
SEE ATTACHMENT
Project Total $196,887.98
Sincerely,
Paul D.Wiegand,P.E.
Public Works Director
Approved
T. Robert Kindred, Assistant City Manager
PDW/kg
c: City Clerk, Finance, Contractor, PW Admin.Asst. , Construction Supervisor
rf
Item Description Unit Price Quantity Total
1 8" sanitary sewer l.f. 24.75 1,415.0 35,021.25
2 Sanitary sewer manhole req'd 11485.00 7.0 10,395.00
3 Std. 8" sanitary plug req'd 30.00 1.0 30.00
4 8" water main l.f. 15.00 1,545.0 23,175.00
5 8" tee req'd 200.00 2.0 400.00
6 8" plug req'd 50.00 2.0 -100.00
7 8" gate valve req'd 450.00 5.0 2,250.00
8 Std. fire hydrant req'd 500.00 6.0 3,00..0.00
9 8" 11+° bend req'd 125.00 2.0 250.00
10 30" RCP storm sewer l.f 40.00 284.0 11,360.00
. 1130" arch RCP storm sewer l.f 58.00 30.0 1,740.00
12 24" RCP storm sewer l.f 30.00 113.0 3,390.00
13 .18" RCP storm sewer l.f 23.00 656.0 - 15,088.00
14 15" RCP sotrm sewer l.f 20.00 170.0 3,400.00
15 12" RCP storm sewer l.f. 18.00 96.0 1,728.00
16 Std. open throat intake req'd 1,100.00 6.0 6,600.00
17 Std. storm sewer manhole req'd 1,100.00 4.0 4,400.100
18 Subgrade preparation S.Y. 1.10 5,700.0 6,270.00
19 Curb and gutter l.f. 8.35 3,060.0 25,551.00
20 Asphalt base ton 27.90 1,531.89 42,739.73
Project Total $196,887.98