HomeMy WebLinkAbout~Master - Completion of Unit No. 8 Waterwall Installation Project RESOLUTION NO. 12-372
RESOLUTION ACCEPTING COMPLETION OF
UNIT NO. 8 WATERWALL INSTALLATION PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Unit No. 8 Waterwall Installation Project for the City of Ames,Iowa,in accordance with a contract
dated April 27, 2010, by and between the City of Ames, Iowa, and AZCO, Inc., of Menasha,
Wisconsin.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Unit No. 8 Waterwall Installation Project has been
fully completed by the Contractor in accordance with the terms of the contract and is
hereby accepted and approved.
Section 2. The total cost of the contract is $3,050,540.15.
Section 3. The amount due AZCO,Inc.,of Menasha,Wisconsin,is hereby ordered paid
as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 10`h day of July, 2012.
_ '`�.x�
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Davis
Seconded by: Goodman
Voting aye: Davis, Goodman, Larson, Orazem, Szopinski
Voting nay: None Absent: Wacha