HomeMy WebLinkAbout~Master - Completion of Precipitator Wire Replacement Project RESOLUTION NO. 12-350
RESOLUTION ACCEPTING COMPLETION OF
POWER PLANT PRECIPITATOR WIRE REPLACEMENT PROJECT
FOR THE CITY OF AMES,IOWA
WHEREAS, the Electric Services Department has filed a certificate of completion for the
Precipitator Wire Replacement Proj ect for the Power Plant for the City of Ames,Iowa,in accordance
with a contract dated September 15,2010,by and between the City of Ames,Iowa,and USCC,Inc.,
of Elizabethton, Tennessee.
NOW, THEREFORE, BE IT HEREBY RESOLVED by the City Council of the City of
Ames, Iowa, as follows:
Section 1. The total contract for the Precipitator Wire Replacement Project for the Power
Plant has been fully completed by the Contractor in accordance with the terms of the
contract and is hereby accepted and approved.
Section 2. The total cost of the contract is $99,201.94.
Section 3. The amount due USCC, Inc., of Elizabethton, Tennessee, is hereby ordered
paid as provided by law.
Section 4. All resolutions or orders or parts thereof in conflict herewith are hereby
repealed to the extent of such conflict.
ADOPTED THIS 26`h day of June, 2012.
c ff l a A. tom• �A++�i
Diane R. Voss, City Clerk Ann H. Campbell, Mayor
Introduced by: Goodman
Seconded by: Larson
Voting aye: Davis, Goodman, Larson, Orazem, Szopinski, Wacha
Voting nay: None Absent: None
Resolution declared adopted and signed by the Mayor this 26t'day of June, 2012.